Wednesday, February 6, 2019

Framing complete - sheathing and roofing almost done

It's been a while since I have updated the blog, and there has been lots of progress. Framing has been completed and the Zip sheathing from Huber which is both airtight and acts as a water barrier has been added as well.

We have received signoff on the framing from both the structural engineer and the county and the next steps are to get the seams between the Zip panels taped and to get the foam-roof built up so that it's ready for the TPO membrane.








The pool company has been repairing and re-installing pipes and pool plumbing. Everything is holding pressure ok and the pool is ready to receive new coping and a new cover.







The foam for the roof was delivered today. Overall our roof assembly is R-64.