Friday, February 17, 2017

Pool progress and drywall wrapping up

The drywall crew is in the process of wrapping up their work. It has taken 4 or 5 layers to get a perfectly smooth level 5 finish on all the interior walls - they have been applying more mud, sanding, checking with side-lights, etc over and over again. Pretty impressive to watch - those guys are magicians.

The pool contractor has begun laying the concrete coping around the pool.








Drywall - third layer

These pictures are from two weeks ago - the next layer of mud was applied and was drying when we took these shots. 

On the outside the stucco scratch coat is drying up nicely












Friday, February 3, 2017

Stucco - first coat complete

Earlier in the week, the first coat of stucco was completed. Now it has to dry for 20 days before they can apply the next coat.