Tuesday, July 19, 2016

Ready for foundation slab inspections

Yesterday the concrete crew finalized all the plumbing, electrical and tension cables in the slab. There were a few changes and tweaks as we reviewed everything, but now everything is ready. In the pictures you can see all the pipes, conduit and the blue tension cable sleeves that will be used to apply tension in the slab after the pour. That creates a very stable and strong foundation.

Here is a shot of the drain, electrical and plumbing running to and from the mechanical room.

 The main house and main living areas over to the right and plumbing for the kitchen island.
 

Reviewing everything and making sure everything is in the right place...